Sybren A. Stüvel 3d606a3fa0 Manager: task scheduler, fix handling of worker assignment of tasks
Improve how the task scheduler deals with tasks that already have a
worker assigned to them:

- When a Worker asks for a task, and there is already an active task
  assigned to it, always return that task.
- Otherwise, never allow scheduling of active tasks, as those are
  already being run by another worker. If this is not the case, their
  status should change to queued/failed, instead of handling the
  situation in the task scheduler.
- Apart from the assigned-and-active case above, ignore task's worker ID
  when scheduling tasks. If the status is 'queued' or 'soft-failed', the
  task's worker ID just indicates who ran the task last.
2022-05-12 13:52:16 +02:00
..